Pretest & Functionally Test All Equipment
to be Commissioned & Correct Deficiencies

Inspect and pretest all major equipment before installation is complete, to discover serious defects that may affect the commissioning and occupancy schedule. Finalize testing once installation is substantially complete, but before full start-up.

Testing should include proper operation of:

  • all motors;
  • all major controls, servos and actuators;
  • pumps; and
  • other electrical and mechanical devices.
  • PV and water solar collectors

Check for correct voltage, starting and operating current, shaft speed, pressure, correct rotation, full travel and positive closure of dampers and valves, etc. Check electrical controls for response to sensors.

All pressure vessels and piping should be pressure- and leak-tested just prior to completion of installation to determine any defects in joints, welds, etc. Ensure that each pretest and test is fully documented, and the records given to the commissioning coordinator.

Caution

  • Ensure lock-out and tagging procedures are rigorously followed for motors and electrical circuits during testing to maintain safety.
Summary of Benefits
Environment
Ease of Use
Other Benefits
Capital Cost 



Home | Whats New | Guidelines in PDF | Site Map  | Design Advisor | Energy Compliance | Contact Us
City of Santa MonicaDesign Credits