GUIDE
CONSTRUCTION WASTE MANAGEMENT SPECIFICATIONS
Adapted
from Los Angeles Solid Resources Management Specification,
LA SRCRD, by Kelly M. Ingalls and Greater Vancouver Regional
District Solid Waste Management Specification, by Susan
Morris Specifications
DISCLAIMER:
THE HEALTH AND SAFETY OF WORKERS AND THE PUBLIC ARE THE
FIRST PRIORITY IN ANY CONSTRUCTION OR DEMOLITION PROJECT.
PROJECT OWNERS ARE RESPONSIBLE FOR COMPLYING WITH ALL APPLICABLE
CODES AND STATUTORY OR REGULATORY REQUIREMENTS. THIS SPECIFICATION
IS NOT INTENDED TO CONSTITUTE OR RENDER ENGINEERING, ARCHITECTURAL,
LEGAL OR OTHER PROFESSIONAL SERVICES OR ADVICE, NOR SHOULD
IT BE A SUBSTITUTE FOR SUCH SERVICES OR ADVICE FROM AN EXPERIENCED
PROFESSIONAL DIRECTED TO THE SPECIFIC DESIGN SITUATION.
WHILE THE INFORMATION IN THE SPECIFICATION IS BELIEVED TO
BE ACCURATE, THE AUTHORS SHALL NOT BE LIABLE FOR DAMAGES
ARISING FROM ERRORS OR OMISSIONS IN THIS SPECIFICATION.
SECTION
01505 - PROJECT WASTE MANAGEMENT
PART
1 - GENERAL
1.1
WASTE MANAGEMENT GOALS FOR THE PROJECT
.1
The Owner has established that this Project shall generate
the least amount of waste possible and that processes shall
be employed that ensure the generation of as little waste
as possible. These shall include prevention of damage due
to mishandling, improper storage, contamination, inadequate
protection or other factors as well as minimizing over packaging
and poor quantity estimating,
.2
Of the inevitable waste that is generated, the waste materials
designated in this specification shall be salvaged for reuse
and or recycling. Waste disposal in landfills or incinerators
shall be minimized. On new construction projects this means
careful recycling of job site waste, on demolition projects
this also means careful removal for salvage.
1.2
RELATED SECTIONS
.1
Section 02050 - Demolition / Dismantling / Salvage
.2
Section 02200 - Earthwork
.3
Section 02870 - Site Furnishings
.4
Section 02900 - Landscaping
.5
Section 03100 - Concrete Formwork
.6
Section 03300 - Cast-In-Place Concrete
.7
Section 05100 & 05400 - Metal Framing
.8
Section 06100 - Rough Carpentry
.9
Section 06200 - Finish Carpentry Cabinets, Countertops
.10
Section 06300 - Wood Treatment
.11
Section 07200 - Building Insulation
.12
Section 08800 - Glazing / Windows
.13
Section 09250 - Gypsum Board
.14
Section 09300 - Tile Work
.15
Section 09550 - Wood Flooring
.16
Section 09650 - Resilient Flooring
.17
Section 09680 - Carpet
.18
Section 09900 - Painting
1.3
CODE OF PRACTICE
.1
In addition to other requirements specified herein it is
a requirement for the Work of this project that the Contractor
comply with the Los Angeles Solid Resources Consolidated
Recycling Division recommendations outlined in publication
entitled Construction and Demolition Waste Recycling
Guide available from the SRCRD, Telephone: (213) 847-1444.
1.4
WASTE MANAGEMENT PLAN
.1
Waste Management Plan: The Contractor shall submit to the
City of Santa Monica Solid Waste Division a Waste Management
Plan pursuant to new SMMC # 7.60. Attached is a sample format
together with sample waste generation rates to aid the Contractor
in formulating the Plan. The Contractor may use this form
or provide a custom form containing the same information.
The Plan shall contain the following:
.1
Analysis of the proposed job site waste to be generated,
including the types of recyclable and waste materials generated
(by volume or weight). In the case of demolition, a list
of each item proposed to be salvaged during the course of
the project should also be prepared (refer to the Waste
Recycling Guide and directory of service providers. This
list is not necessarily complete. The Contractor may use
any of these or other licensed service providers).
.2
Alternatives to Landfilling: Contractor shall designate
responsibility for preparing a list of each material proposed
to be salvaged, reused, or recycled during the course of
the Project
.3
List of compulsory materials to be recycled, shall include,
at minimum, the following designated materials:
.1
Old corrugated cardboard.
.2
Clean dimensional wood, palette wood.
.3
Concrete/Brick/Concrete Block/Asphalt.
.4
Scrap Metal.
.5
Drywall.
.6
Land clearing debris.
.7
Paint (return to hazardous waste depot).
.4
List of optional materials to be salvaged (demolition projects
only)
.1
Dimensioned lumber and heavy timbers.
.2
Wood siding.
.3
Structural steel.
.4
Wood paneling, molding, trim and wainscoting.
.5
Heritage architectural elements such as mantle pieces, columns,
etc.
.6
Cabinets and casework.
.7
Insulation, where suitable.
.8
Brick and block.
.9
Electric equipment and light fixtures.
.10
Plumbing fixtures and brass.
.11
Windows, doors and frames with historic value.
.12
Hardwood flooring.
.5
Meetings: Contractor shall conduct Project Waste Management
meetings. Meetings shall include subcontractors affected
by the Waste Management Plan. At a minimum, waste management
goals and issues shall be discussed at the following meetings:
.1
Pre-bid meeting.
.2
Pre-construction meeting.
.3
Regular jobsite meetings.
.6
Materials Handling Procedures: prevent contamination of
materials to be recycled and salvaged, and handle materials
consistent with requirements for acceptance by designated
waste-disposal facilities. Where space permits, source separation
is recommended. Where materials must be commingled they must
be taken to a processing facility for separation off site.
.7
Transportation: The Contractor may engage a hauling subcontractor
or self haul or make each subcontractor responsible for
their own waste. In any case compliance with these requirements
is mandatory. .
8
If requested, submit to the Consultant and/or Owner way-bills,
invoices and other documentation confirming that all materials
have been hauled to the required locations. Way bills may
be requested by the building authority.
1.5
WASTE MANAGEMENT PLAN IMPLEMENTATION:
.1
Manager: The Contractor shall designate an on-site party
(or parties) responsible for instructing workers and overseeing
and recording results of the Waste Management Plan for the
project.
.2
Distribution: The Contractor shall distribute copies of
the Waste Management Plan to the Job Site Foreman, each
Subcontractor, the Owner, and the Consultant.
.3
Instruction: The Contractor shall provide on-site instruction
of appropriate separation, handling, and recycling to be
used by all parties at the appropriate stages of the Project.
On demolition projects the Contractor shall provide on-site
instructions for salvage and requirements for reusing salvaged
materials within the project, either in new construction
or in a renovation.
.4
Separation facilities: The Contractor shall lay out and
label a specific area to facilitate separation of materials
for recycling and salvage. Recycling and waste bin areas
are to be kept neat and clean and clearly marked in order
to avoid contamination of materials. The requirement for
separation will only be waived if the Contractor can demonstrate
to the Owner/Consultant that there is insufficient room
to accommodate it. If this is the case the materials must
be sent to a processing off-site facility for separation,
salvage and recycling.
.5
Hazardous wastes: Hazardous wastes shall be separated, stored,
and disposed of in accordance with the requirements of the
authorities having jurisdiction, including Federal, State,
County and City agencies.
.6
Application for Progress Payments: The Contractor shall
submit with each Application for Progress Payment a summary
of waste materials, recycled, salvaged and disposed of by
the Project using the form appended to this specification
or a form generated by the Contractor containing the same
information. Failure to submit this information shall render
the Application for Payment incomplete and shall delay Progress
Payment. The Summary shall contain the following information:
The
amount (in cubic yards or tons) of material landfilled from
the Project, the identity of the landfill or inert fill
site and/or transfer station. For each material recycled
or salvaged from the Project, include the amount (in cubic
yards or tons or in the case of salvaged items state quantities
by number of items) and the destination (i.e. the material
recovery facility, transfer station, landfill, or used building
materials yard).
END
OF SECTION 01505